§25.1725 Powerplants; EWIS

CS-25 · Subpart H — Electrical Wiring Interconnection System · at CS25-28 (current)

Text in force at CS25-28: from CS25-5, effective 5 Sep 2008.

(a) EWIS associated with any powerplant must be designed and installed so that the failure of an EWIS component will not prevent the continued safe operation of the remaining powerplants or require immediate action by any crew member for continued safe operation, in accordance with the requirements of CS 25.903(b). (b) Design precautions must be taken to minimise hazards to the aeroplane due to EWIS damage in the event of a powerplant rotor failure or of a fire originating within the powerplant, which burns through the powerplant case, in accordance with the requirements of CS 25.903(d)(1).

ED Decision 2008/006/R · Source

Report an issue

Report an issue

Is something wrong with what you are looking at? Tell the maintainer; the report is filed against this page.

What kind of issue is it? (required)

Reports are posted publicly on GitHub with the address of this page. Please don't include personal information.